The foundation walls were poured before we headed to Lake Powell. Then the concrete had to cure a little. Dirt was brought back in to fill in the footing area...and the basement plumbing was put in place. The heater/AC vents are now in the basement. The steel beams are now in place so that the garage floor can be poured next week. The basement floor will also be poured next week. Then the framers will be able to come! We are getting really excited. The house is starting to take shape and we can really see the shape of it. I plan to meet with the cabinet designer this next week to finalize our plans and then I will meet with Dave at Orson Gygi to finalize the appliances.